German is approving more housing again. Whether much of it can be financed and built is another matter. The Federal Statistical Office reported on 16th October that permits were granted for 20,600 homes in August, 6.8% more than a year earlier. Between January and August, 169,400 homes were approved, an increase of 12.1%, with approvals in new multifamily buildings rising by 14.5% to 90,600. Student residences moved in the opposite direction, falling by 2% to 5,300.
The recovery starts from a low base: the eight-month total remains around one-third below 2021, when more than 250,000 homes were approved over the same period, according to Felix Pakleppa, chief executive of the construction federation ZDB. More importantly, permission is no longer the principal obstacle. By the end of 2025, the ZDB estimates, around 450,000 approved homes had yet to proceed because building them was not financially viable, and completions fell to 206,600 last year, the lowest since 2012. Jan-Marco Luczak, the CDU/CSU parliamentary group’s construction spokesman, welcomed the improvement but put its limitation plainly: “Nobody can live in a building permit.”
The improvement in permits has arrived without a corresponding improvement in the conditions needed to turn them into completed homes. Following the European Central Bank’s rate increases in June and September, ten-year housing-finance rates have moved above 4% in parts of the market. Energy and materials have become dearer since the escalation of the war in Iran, and residential construction prices rose by 5.5% in the year to August. The ifo business climate for residential construction fell to −25.1 in September from −22.5 in August, with companies markedly more pessimistic about the months ahead.
The federal government offers its balance sheet
The proposed answer is to use the federal balance sheet where private development finance no longer works. Construction Minister Verena Hubertz and Finance Minister Lars Klingbeil are planning a federally controlled housing company to begin operating in 2027. The federal government would own 51%, with the remaining 49% open to private investors and municipal or state-owned housing companies. Hubertz describes it as a lean organisation rather than another government agency, commissioning developments from market participants instead of building itself.
Its intended advantages are purchasing power and cheaper capital. Large, repeatable orders could secure lower prices and give serial and modular builders the volumes they need, while federal ownership would allow the company to borrow on terms reflecting Germany’s credit standing rather than those available to an individual developer.
The diagnosis has some merit. If expensive finance is preventing approved housing from being built, a sovereign balance sheet addresses the constraint directly. Less obvious is the conclusion that Germany therefore needs another public institution. After years of missed housing targets, the government must explain why existing development banks, subsidies and public housing companies cannot deploy the same financing advantage more quickly.
That does not yet make the proposal a housing programme. The ministry has promised a fuller concept this autumn, although none had appeared by mid-October. Three tests will determine whether the company adds homes or merely adds another institution.
The first test concerns its legal and financial framework. Housing policy and implementation are principally responsibilities of the Länder, and the IMK institute of the Hans Böckler Foundation has warned of constitutional risks. It proposes federal guarantees or direct loans, potentially through KfW, for housing companies committing to affordable rents. That less dramatic solution could transmit the same financing advantage through organisations that already own land, manage homes and commission construction.
The surrounding policy is also pulling in the opposite direction. The ZDB calculates that federal support for new construction is due to fall by more than 40% in 2027, the year in which the company is expected to begin work. Pakleppa called that the worst possible signal for builders and investors requiring dependable conditions.
The difficult part is execution
The second test is additionality and speed. It remains unclear whether the company would develop federal land, purchase sites, commission new projects or activate approved but stalled housing. If it merely competes with existing developers for the same sites, contractors and materials, cheaper finance may change who builds the homes without increasing how many are built. For now, the proposal remains a financing concept in search of a pipeline.
The 450,000 approved but unbuilt homes provide an obvious starting point, although not all can or should be rescued. Some will be impaired by expensive land purchases, unsuitable designs or assumptions about rents and selling prices that no longer hold. The useful measure will be the number of otherwise viable projects that federal participation can move from permit to construction. Speed will matter as much as scale: a vehicle designed to overcome delays will be judged harshly if it becomes another source of them.
The third test concerns the terms on which the remaining 49% will be offered. Participants will need to know what they are being asked to finance, what returns and governance rights they will receive, who bears development, cost-overrun and letting risk, which rent and affordability commitments attach to the cheaper capital, and how minority shareholders may exit.
Those questions expose the difficulty at the centre of the proposal. The federal government wants private expertise and capital, but also control, affordable rents and lower return expectations. That combination is possible only if the value of cheaper land, finance or procurement compensates participants for the restrictions placed upon them.
The rise in permits shows that developers are again willing to prepare housing, but it does not show that those homes can be financed and built. The federal company at least recognises that the blockage has moved from permission to viability, but recognition, given the government’s record of missed housing targets, is not much of an achievement.
The promised concept must show how federal credit will reach construction sites quickly, unlock homes that would otherwise remain on paper and attract outside partners on workable terms. Germany has no shortage of institutions capable of announcing housing targets. What it lacks is delivery.